Case Study • Food & Beverage Retail
Albertsons CIP System & Air Farm
State-of-the-Art System installed with zero unplanned downtime
Completed cleanly in exactly three brief outages. Detailed offsite prefabrication and strategic scheduling allowed full replacement with zero unplanned disruptions.
Fast-Track Turnkey Execution Timeline

Active Plant Setup
Live Albertsons production operations
Surgical Accuracy
Engineered offsite preassembly stages
Contained Outages
All cuts conducted under 4 hours
Continuity Achieved
100% operational throughput preserved
Key Performance Successes
Critical Timelines • High Performance Results
3 Outages
Completed Outage Count
All installation phases achieved sequentially via three planned interruptions.
<4 Hrs
Maximum Planned Outage
Strict deadline control applied to ensure zero material or manufacturing delays.
0 Disruption
Unplanned Interruption
Facility preserved full commercial continuity with zero margin of error allowed.
100% Go
Continuity Maintained
Sanitized delivery lines fully active with next-generation utility systems online.
Case Context
The Challenge: Replace Critical CIP and Air Systems with Virtually Zero Downtime
Albertsons required a major utility modernization at their active production plant. They needed to fully replace aging Clean-In-Place (CIP) assets and optimize their foundational pneumatic Air Farm infrastructure.
At a high-volume retail supply facility, taking main production systems offline would cost substantial volume. DPS had only three planned outage windows, none of which could exceed four hours under any situation. Perfect, fast validation of connections was the key requirement.
DPS METHODOLOGY
Design • Build • Manage – Dynamic Alignment
Stage One
DESIGN
Detailed pre-planning and 3D modeling. Piping and valve matrixes modeled off-site to match plant ports perfectly and compress on-site structural modifications.
Stage Two
BUILD
Field prefabrication of manifolds, skid frames, and air conduits. Real-time physical rigging sequences pre-drilled to ensure connection drops were completed cleanly under deadline pressures.
Stage Three
MANAGE
Strict execution checklists tracking minute-by-minute progress. Successfully completed all three tie-ins on budget and ahead of time, ensuring Albertsons maintained full market operation with zero supply disruptions.
EXECUTION TIMELINE
Phased Modernization & System Integration
Turnkey Delivery Completion
Pre-Outage
Engineering & Prefabrication
Offsite fabrication of CIP skids. Material procurement set and local field resources fully mobilized.
Outage 1
< 4 Hours
First tie-in completed. Primary CIP lines cut over and initial process piping validations released cleanly.
Outage 2
< 4 Hours
Air Farm manifolds integrated and pneumatic line pressure checks executed concurrently without delay.
Outage 3 🎉
< 4 Hours
Final integration loop finalized. System validation and dry run cycles safely completed inside the final planned limit.
Post-Outage
Full Integration
New utilities running at full commercial capacity with 100% operational supply chain maintained.
PROJECT GALLERY
Installation & Integration Phase Images
Rigging & Positioning Sequence
Rigging and Prep Section
Hygienic Valve Assembly Panel
Structure Supports Anchoring
Fluid Holding Systems Staging
Pneumatics Compressor Terminal
Overhead Fluid Utilities Header
Stainless Skid Mount Anchors
Utility Wall Sleeve Terminations
Valves Line pressure fitting
Stainless Steel Frame Ground Leveling
Vertical Storage Vessel Isolation
Sanitary Tubing Pre-weld alignment
Process Water Valve Matrix
Industrial Fluid Heat Exchanger Module
Orbital Weld Precision Run
Utility Lines Structural Anchoring
PLC Panel Terminations Step
Staging Area Layout Prep
Field Calibration Loops Integration
Air Line Filtration Units
Receiver Isolation Valves Alignment
Utility Lines Pressure Decay Testing
Control Panel Solenoid wiring
SCADA dry-run verification sequence
Validation & Verification Checks
Final Clean Sequence Dry RunCLIENT VOICE
“DPS executed this critical upgrade with incredible precision. We experienced zero unplanned downtime across three separate outages. Every minute truly counted — and they delivered.”
Facilities Engineering Manager
Albertsons Companies
IMPACT HIGHLIGHTS
- Total Outages Scheduled
- 3 (all < 4 hrs)
- Unplanned production loss
- Zero
- Piping Integration efficiency
- 100% Successful
Connect With Senior Engineering Specialists
Connect With our CIP Upgrade Architects
Let’s map out how DPS can deliver your next facility modernization, line expansion, or complex process plant retrofit with absolute timing precision and zero commercial lag.
Confidential Engineering Feasibility Request
